Default duration on the timeline of Roll title.

Nov 28, 2013 4:22 AM

Tags: #importer_api #premiere_pro_sdk

We are developing a title importer plugin for Premiere Pro CC.

 

I want to set a default duration value when I put materials on the timeline.

However, selector imGetInfo8 is called, if imFileInfoRec8->vidInfo.isRollCrawl=1 is returned, the value of General Setting will be effective.

 

It is supplementary as follows:
1.materials is a roll/crawl title.
2.The roll/crawl title made by our software.
3.roll/crawl title has duration.
4.The roll/crawl title in the timeline already, I want to change the duration freely.
5.It is not reflected although imFileInfoRec8->vidDuration was tried.


Is it possible in Premiere Pro SDK ?

 

Best Regards.

 
Replies
  • Currently Being Moderated
    Dec 2, 2013 4:11 PM   in reply to H.T

    Hi H.T

     

    At this time, roll/crawl titles cannot be initialized with a non-default length.  So you would need to choose between implementing your titles as roll/crawl titles, or as normal video where the length can only be adjusted in the setup dialog.

     
    |
    Mark as:

More Like This

  • Retrieving data ...

Bookmarked By (0)

Answers + Points = Status

  • 10 points awarded for Correct Answers
  • 5 points awarded for Helpful Answers
  • 10,000+ points
  • 1,001-10,000 points
  • 501-1,000 points
  • 5-500 points