craiglaw98 wrote:
> if i had 10,000 records, the scheduled task starts to
process, what happens if
> this process takes longer than 61 secs, will the next
scheduled task start, or
> would it only run once the first task is complete?
The former. As far as the web server and ColdFusion is
concerned a
scheduled task is simply a client requesting an URL little
different
then if a human requested the URL with a desk top browser. So
you want
to take all the care of making sure your schedule task code
can handle
multiple, overlapping requests. Just as if you where building
it for
human users who could make more then one request at the same
time.