      Hi,

       

      We are using multiple instances of InDesign CC Server 2015 along with LBQ on a Windows Server 2012.

       

      LBQ log files show an error communicating with one the IOR files, and tells that the job will be requeued. But for some unknown reason, the job is not rescheduled before a little more than 10 minutes, meanwhile some IDS instances got free at some point.

       

      I can't seem to find any explanation on why this wait time gets so long.. Is there any kind of configuration (like a wait time for rescheduling or something else) I've missed ?

       

      Would it be possible to automatically raise priority for a job planned to be requeued ?

       

      Thanks for your help.

       